Overall equipment effectiveness (OEE)

OEE measures how much of a machine’s planned production time is truly productive, combining availability, speed and quality.

How to calculate it

OEE % = Availability % × Performance % × Quality %

Worked example (illustrative numbers)

  • Availability: 90%
  • Performance: 95%
  • Quality: 98%

Result: 83.8%. 83.8%: three strong-looking numbers multiply into one that shows about a sixth of planned time is lost.

What good looks like

85% is the figure commonly cited as world-class for discrete manufacturing.

Common mistakes

  • Excluding changeovers and planned maintenance from planned time to flatter availability.
  • Measuring quality at final inspection only and missing rework.

Review it weekly.

Read it with